Indirect costs in construction
Indirect costs (or indirect spend) are those costs that are necessary to keep a process or project running, but which do not vary directly with the volume of goods or services produced and are not easily attributable to a particular process or project. This might for example include; rent, insurance, advertising and marketing and so on. These types of indirect costs may be referred to as overheads.
This is as opposed to direct costs, which are those costs incurred directly by production and include items such as raw materials, labour, equipment, power and so on. Direct costs can be traced and are attributed to a cost ‘object’ which may be a product, department, cost centre or project.
So, indirect costs do not vary directly with production levels, whereas direct costs remain dependent on production levels and will vary when production is increased or decreased.
NB Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines indirect costs as: ‘…costs incurred during construction works that cannot be attributed to any one section of the works; they may be fixed (e.g. the cost of bringing accommodation to the site) or time-related (e.g. the cost of insurance or security personnel).’
For more information see: Direct costs.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.
The adaptive reuse of large industrial structures.
Promoting the circular economy by extending the life of buildings.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.
Construction Management, 17 June
Government rolls out digital planning tool to all local authorities.
Your views needed - a strategy for the professions, trades and occupations.
Confronting competency, codes, capacity and costs.


















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
I would like to know if prelim, overheads and profits are considered as "indirect costs"
They are typically considered to be indirect costs.